Exercise: Developing an O&M plan for your adaptation project

   Analyse your adaptation measure using
      worksheet 3 of handout 7.1 and design an
      operation and maintenance plan by using a
      four-step approach:

    First step: Define the components: Of what
       components is your measure composed of?

    Second step: Analyse and define what O&M
       activities are necessary to operate and maintain
       the infrastructure measure.

   Third step: Define the timetable: when is the
       action to be realised or may it be a returning
       activity and on what frequency it must be
       implemented?

   Fourth step: Who is responsible for each
       identified O&M activity? Should there perhaps
       be a person employed just for that task?